CMA is providing all the detailed design and engineering for all disciplines (mechanical, civil, structural, electrical & architectural) as well as structural and equipment detail fabrication drawings pertaining to the following mill upgrades at West Fraser’s Bemidji OSB mill:

  • Fuel conveying and storage systems
  • Wet strand storage system
  • Strand conveyor system
  • Heat energy system
  • Strand drying system
  • Abatement system
  • Dry strand storage system
  • Primary and secondary screening systems
  • Blending system

CMA is also providing the budget and schedule preparation for the project.

Project value: Approx. $190M